The Concrete Pour for the Footing is Finished

IMGP5219

Yesterday morning, the township building inspector inspected the footing and passed us. John immediately called Main Line Concrete for the concrete pour. (The cost of the pour with 3 yards of concrete was $535.00).

The truck arrived at 2pm and John told Matt, the driver, to back in as close as he could avoiding the Japanese maple tree. The concrete truck was a smaller size but still too large to reach the footing at the back of the house.

IMGP5220IMGP5221

“Get a Load Out of This!”

IMGP5228

The truck couldn’t make it underneath the maple tree; there was a large handle attached to the left side of the truck which prevented it from reaching the footing (it would have hit the tree).

IMGP5231

Matt got the scoop ready for the first wheel barrow. He sprayed it with his hose and within a few minutes the first batch of concrete slid down the scoop and into the wheel barrow.

IMGP5232

John and his friend, Jon, started on the north footing first so they could fill the trench toward the truck. This was the very first wheel barrow load of cement. Doing this work was LABOR INTENSIVE. Additionally, it was 95 degrees with extreme humidity. They were sweating buckets, literally. It was also the hottest part of the day.

IMGP5233

IMGP5235

They continued dumping concrete in the footing. Each wheel barrow required two men, so  the job required at least three men, but ideally four. They had to roll the wheel barrow down a plywood ramp that John placed across the trench.

IMGP5236

After a few loads of concrete, John used a shovel to eliminate any bubbles. He agitated the concrete by pushing the shovel up and down forcing the bubbles out of voids.

IMGP5237IMGP5238

The concrete was dumped inside the wood forms. John made sure the concrete was filled to the top of the forms and then spread evenly as he moved down the trench.

IMGP5241

Moving along…it takes time to fill the form up with concrete.

IMGP5242

Everyone really had to hustle because we were allowed a certain amount of time with the concrete truck. The truck was on site for a total of one hour and 15 minutes. Any longer and it would have cost us more money.

IMGP5247

Soon after starting, Jack, a helper showed up to help with dumping the concrete in the trench.

IMGP5249

This is the ramp where they rolled the wheel barrows over. It took a second man holding the front end of the wheel barrow to get it over the edge of the ramp preventing the concrete from slopping over the edge.

IMGP5252

After agitating the concrete, John used a trowel to smooth out the cement.

IMGP5253

At first, John agitated with a shovel, but when Jack arrived, he said a metal rake is much better to use for getting the bubbles out. (Bubbles will create cracks in a foundation).

IMGP5258

The metal rake made a huge difference. Thanks for the tip, Jack!

IMGP5259

As Jack and Jon dumped the cement, John told them where to guide the wheel barrow so that the cement accurately fell within the forms. Otherwise, cement would fall outside of the form–using extra cement is extra money needlessly spent.

IMGP5248

Moving down to the corner for leg two…

IMGP5260

About to round the corner…

IMGP5269

It was blazing hot with intolerable humidity. But timing is everything and we had to get this done before a forecast of rain. It hurt to watch men in their 50s do this kind of work in extreme heat.

IMGP5271

Using the trowel again…

IMGP5272

I was standing at the open back door telling Jack and Jon where to dump the wheel barrows. About the only thing I could have done is agitate the concrete but if I had done that I would not have gotten all of the photos.

IMGP5278

I like Jack’s shirt, after the whole renovation is complete, maybe we’ll be singing for food.

IMGP5280

We had to fill a smaller footing as well…

IMGP5282

We all joked and said it looked like quick sand…

IMGP5285

It’s like cake batter… when John worked for a builder, they had done several footings.

IMGP5284

Almost finished…

IMGP5289

Time to leave our stamp…

IMGP5291

And…

IMGP5297

We can’t forget Jon and Jack’s initials…

IMGP5299

Without their help with the footing job, we’d be going nowhere fast…

IMGP5307

Can’t forget the paw print…what fun!

IMGP5311

VOILA!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!

 

 

 

 

 

 

 

 

Leave a Reply

Your email address will not be published. Required fields are marked *

*